Wednesday 8 March 2017

Completed up to the "ivy" section

A decision was taken not to dismantle the ivy covered section, but just rebuild the collapsed top section.  So whilst Barry, Catriona, Matthew and Richard worked on completing the remaining top courses, Tony tackled the "ivy" gap.

During the day we were honoured by a visit from Ian and Deirdre Curteis to check on our progress. We also had a group of  lady walkers stop to chat about what we were doing.


The ivy gap


After lunch it was time to tackle the next section of the wall



The next section at close of play

The completed wall up to the ivy section from both sides



Tony H
No of wallers 5

No comments:

Post a Comment